INVESTMENT ACTIVITIES

GRI 203-1

Investment activities are one of the key areas of the general development strategy of the Company and is intended to ensure the growth of operating profit.

Investment activities are aimed towards augmenting the reliability and enhancing the operation of the power grid complex, as well as reducing losses in electric gridsThe final draft of amendments to the investment programme of PJSC Rosseti South for 2023 was approved by Order No. 13@ of the Ministry of Energy of the Russian Federation dated 8 December 2023 “On approval of the investment programme of PJSC Rosseti South for 2024–2028 and amendments to the investment programme of PJSC Rosseti South approved by Order No. 31@ of the Ministry of Energy of the Russian Federation dated 24 November 2022”..

INDICATORS FOR INVESTMENT ACTIVITIES

Progress on the investment programme

Indicators

UoM

Period

2021, actual

2022, actual

2023, actual

Change 2023/2022, %

Amount of funding

RUB mln

7,008

4,813

5,417

113

Utilisation of capital investment

RUB mln

4,938

4,050

3,445

85

Additions to fixed assets

RUB mln

6,268

3,417

3,523

103

Commissioning of transformer capacity as part of fixed assets

MVA

668

325

115

35

Commissioning of power transmission lines as part of fixed assets

km

861

594

681

115

Long-term investment programme for 2024–2028

Indicators

UoM

Period

2024

2025

2026

2027

2028

Amount of funding

RUB mln

4,652

3,955

3,117

3,639

3,325

Utilisation of capital investment

RUB mln

3,087

3,134

2,848

2,786

2,304

Additions to fixed assets

RUB mln

3,276

3,165

2,978

2,657

2,363

Commissioning of transformer capacity as part of fixed assets

MVA

88

82

77

34

63

Commissioning of power transmission lines as part of fixed assets

km

554

466

397

382

314

The majority of investments made within the area of grid connection operations went towards executing the agreements for the grid connection of a privileged group of customers with connected capacities of up to 15 kW. The amount of funding for these activities in 2023 totalled RUB 2,125.76 million, or 62% of the total funding for grid connection.

The main volume of investment activities related to renovation, upgrade and retrofitting included financing of measures for development and upgrade of electricity (capacity) metering, namely RUB 936 million, or 56% of the total retrofitting and upgrading financing.

In order to monitor progress in implementing investment programmes and priority investment projects, Rosseti adopted Order No. 165r dated 31 March 2023 “On Approval of the List of Priority Facilities to be Implemented at Rosseti’s S&As and Other Controlled Entities” to approve the list of priority facilities of Rosseti’s S&As for 2023.

In 2023, the majority of the funding for investment projects went into two categories of initiatives:
  • grid connection – RUB 3,431 million (VAT included), or 63% of total investments
  • renovation, upgrade, modernisation, retrofitting – RUB 1,658 million (VAT included), or 31% of the total funding
In accordance with the approved investment programme, the Company launched one priority investment project in the reporting year:

GRI 203-1

Renovation of AC1 110 kV substation with replacement of 2×10 MVA transformers with 2×16 MVA transformers

In 2023, a design and survey contract was concluded and the main technical solutions and design documentation were developed. The commissioning of the facility is scheduled for the 4th quarter of 2026.


The purpose of the renovation of the AC1 110/10 kV substation is to unload the closed power supply centre, to eliminate the existing risks of the power system operation parameters exceeding the permissible limits, and to ensure the reliability of consumers in the Aksay district of Rostov Region.

The investment project is aligned with the approved Order of the Ministry of Energy of the Russian Federation No. 1095 dated 30 November 2023 of the Scheme and Programme of Development of Power Grid Systems of Russia for 2024–2029.

Capital investment structure, RUB mln, including VAT

Indicators

2021

2022

2023

Total

7,008

4,813

5,417

Grid connection

4,329

2,130

3,431

Renovation, upgrading, modernisation, retrofitting

2,598

2,630

1,658

Investment projects, which are subject to the schemes and programmes for the prospective development of the electric power industry

0

2

1

Other new construction of power grid facilities

1

0

0

Purchase of land parcels for investment projects

4

0

0

Other investment projects

76

51

327

Funding of the investment programme by source for 2023:

Investment Programme financing sources in 2023, RUB mln, incl. VAT, and %
Investment Programme financing sources in 2023, RUB mln, incl. VAT, and %

Long-Term Investment Programme

The Investment Programme of PJSC Rosseti South for 2024–2028 was approved by Order No. 13@ of the Ministry of Energy of the Russian Federation dated 8 December 2023.

Parameters of investment activities as envisaged in the long-term investment programme

Year

Astrakhanenergo

Volgogradenergo

Kalmenergo

Rostovenergo

Rosseti South

2024

973

686

283

2,710

4,652

2025

750

543

142

2,519

3,955

2026

580

496

110

1,931

3,117

2027

804

680

110

2,044

3,639

2028

804

680

110

1,731

3,325

Changes in commissioning of transmission lines for 2024–2028, km

Year

Astrakhanenergo

Volgogradenergo

Kalmenergo

Rostovenergo

Rosseti South

2024

144

74

57

279

554

2025

101

99

54

212

466

2026

115

64

44

173

397

2027

110

76

44

152

382

2028

91

43

44

137

314

Changes in capacity commissioning for 2024–2028, MVA

Year

Astrakhanenergo

Volgogradenergo

Kalmenergo

Rostovenergo

Rosseti South

2024

45

4

1

38

88

2025

11

6

1

64

82

2026

9

3

1

64

77

2027

10

3

1

20

34

2028

10

2

1

51

63

Changes in commissioning volumes for 2024–2028, RUB mln, excluding VAT

Year

Astrakhanenergo

Volgogradenergo

Kalmenergo

Rostovenergo

Rosseti South

2024

736

566

147

1,828

3,276

2025

413

464

124

2,164

3,165

2026

592

398

91

1,896

2,978

2027

627

548

91

1,391

2,657

2028

634

397

93

1,240

2,363

Changes in drawdown volumes for 2024–2028, RUB mln, excluding VAT

Year

Astrakhanenergo

Volgogradenergo

Kalmenergo

Rostovenergo

Rosseti South

2024

617

552

155

1,763

3,087

2025

523

463

118

2,030

3,134

2026

497

478

91

1,783

2,848

2027

617

524

91

1,555

2,786

2028

634

468

92

1,110

2,304

The Long-Term Investment Programme for 2024–2028 envisages capital investment of RUB 14,159 million, excluding VAT, financing of RUB 18,687 million, including VAT, commissioning of fixed assets of RUB 14,439 million. Between 2024 and 2028, it is planned to re-build and renovate 2,114 kilometres and commission 345 MVA of transformer capacity.

CAPITAL CONSTRUCTION QUALITY CONTROL

In order to verify compliance of the works performed with the design documentation, requirements of technical regulations, results of engineering surveys, requirements of the town-planning plan of the land plot in the process of construction, renovation, overhaul of capital construction facilities In accordance with Article 53 of the Town-Planning Code of the Russian Federation under Resolution No. 468 of the Government of the Russian Federation dated 21 June 2010 “On the procedure for construction control during construction, renovation and overhaul of capital construction projects”. , the Company carries out construction supervision Regulated by the Procedure for Construction Control at Power Grid Facilities of PJSC Rosseti South approved by Order No. 174 of PJSC Rosseti South dated 10 March 2020..

By the end of 2023, the quantitative indicator of the coverage of independent construction supervision of facilities of 35 kV and above class under construction reached 67%.

Distribution of M&R costs for 2020–2024, RUB mln
Distribution of M&R costs for 2020–2024, RUB mln

Distribution of maintenance and repair costs between in-house and contractual methods for 2020–2024, RUB mln
Distribution of maintenance and repair costs between in-house and contractual methods for 2020–2024, RUB mln

Maintenance and repair component in 2020–2024 tariffs
Maintenance and repair component in 2020–2024 tariffs

With timely and full maintenance and repair, power grid assets at the Company’s branches were successful prepared for peak loads in the autumn and winter period and consumers within Rosseti South’s area of responsibility enjoyed reliable power supply.

Preparedness to respond to potential process-related faults

Regardless of the time of year and weather conditions, Rosseti South’s employees are prepared to respond to potential process failures: 672 teams (3,427 people, 1,686 units of equipment), including 44 mobile teams (266 people and 116 units of equipment), are prepared for emergency recovery work and large-scale outages, and can be sent out to help other subsidiaries and affiliates of PJSC Rosseti, if necessary. Moreover, 209 emergency repair crews of contractors can be involved in power supply restoration. There are 334 reserve power supply sources with a total capacity of 13.9 MW.

Training in natural and man-made emergency prevention and response is arranged on an ongoing basis with the involvement of 100% of the management and other personnel of PJSC Rosseti South.

Eight joint exercises were held with the headquarters for ensuring the security of electricity supply in the constituent entities of the Russian Federation, territorial executive authorities and local governments, the Ministry of the Russian Federation for Civil Defence, Emergencies and Elimination of Consequences of Natural Disasters, and housing and utilities organisations to practice emergency response skills.

Results_Grigorenko_(52).png